Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

You are the project manager at a utility company. Due to the recent rise in the cost of petroleum, your organization is exploring cheaper, ?

alternative forms of energy. You have just completed the project scope changes, requested changes, and updates to the project scope management plan. Which of the following process did you just complete? A. Develop preliminary project scope statement B. Scope definition C. Scope planning D. Scope verification E. Develop project management plan

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2019/05/08
Haiam Al -Uaimer
par Haiam Al -Uaimer , Accounts Director , Almond

As the project manager at a utility company facing higher petroleum costs, the organization is actively exploring cheaper and more sustainable energy alternatives. Key strategies include investing in renewable energy sources like solar, wind, hydro, and geothermal power, implementing energy efficiency initiatives, deploying smart grid technology, and promoting demand response programs. Energy storage solutions, diversification of energy sources, and securing long-term contracts are also considered to reduce vulnerability to petroleum price fluctuations. The utility company aims to optimize energy usage, lower operational expenses, and contribute to a greener and more sustainable energy future through these efforts.

amjad iqbal
par amjad iqbal , Group Product Manager , Shaigan Pharmaceutical Pvt. Ltd Pakistan

A: Scope definition

B: Develop preliminary project scope statement

C.  Scope planning

D. Scope Management & verification

E. Develop project management plan

F: Project Managment & Human Resource Management

Ashraf Alja'fari
par Ashraf Alja'fari , Integrated Shipping Manager , Amin Kawar And Sons Company

C.

The statement comes first along with the definition and verification + develop comes after the planning.

QUDRATH ALI MOHAMMED
par QUDRATH ALI MOHAMMED , Sales Executive , Airlink International UAE

 A. Develop preliminary project scope statement

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. Scope definition -----------------

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?