Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

I am represending the contractor. the project was delayed due to asses problem. consultant recommending extension of time without cost. how to face

the consultant ready to give extension of time without cost. the contractor are to bear the cost of over head during this extension. we see this is unfaire. how to tackle this problem.

user-image
Question ajoutée par firdous Abdul caffoor mohammed , Projects Manager , Maga Engineering (Pvt) Ltd, Sri Lanka
Date de publication: 2014/07/08
Shabbir Ali Mirza
par Shabbir Ali Mirza , Contracts Administrator , Pivot Engineering and General Contracting LLC

First of all I would request that we all shall make sure that spelling mistakes or typo errors are eradicated prior to posting questions.

Regarding the issue of the Engineer being unfair, the whole notion of having standardized Conditions of Contract is to make sure that justice prevails and served to all parties involved in any given Contract.

as rightly said by Mr. Stella above "prepare a cost valuation related to prolongation of the project and timely notice the Consultant about your claim.

Abdul Wahab Mohamed Azmy
par Abdul Wahab Mohamed Azmy , Chief Accountant , Bahrain Development Centre

Some contract administrators are of the view that submission of a well documented extension of time claim is a condition precedent to the contract administrator’s obligation to grant an extension of time.

 

If the contractor fails to submit relevant details to the contract administrator then the latter is not obliged to evaluate the contractor's claim or at the very least delays in granting an extension of time until the relevant information has been submitted. Contractors often view this as a delaying tactic by the contract administrator or even accusing the contract administrator of not carrying out his impartial duty to evaluate for the contractor's entitlement to extension of time especially where delays are caused by the employer. 

G S
par G S , Senior lawyer , National Union of Attorney at Law of Romania

Above all, you shall prepare a cost valuation related to prolongation of the project and timely notice the Consultant about your claim.

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?