Trending Thermal Processing Discussions

Follow

Ask the Community


Ask any professional question and get answers from other specialists.

Stream language
Naushad Parappummal's image
Question added by Naushad Parappummal Executive Engineering Siemens Limited
10 years ago
Answers:
2
Followers:
Views:
238
Vote Count:
0
Answer should contain a minimum of 25 characters.
Naushad Parappummal's image
Question added by Naushad Parappummal Executive Engineering Siemens Limited
10 years ago
Answers:
2
Followers:
Views:
238
Vote Count:
0
Answer should contain a minimum of 25 characters.
Naushad Parappummal's image
Question added by Naushad Parappummal Executive Engineering Siemens Limited
10 years ago
Answers:
2
Followers:
Views:
152
Vote Count:
0
Answer should contain a minimum of 25 characters.
Naushad Parappummal's image
Question added by Naushad Parappummal Executive Engineering Siemens Limited
10 years ago
Answers:
0
Followers:
Views:
79
Vote Count:
0
Answer should contain a minimum of 25 characters.
Ahmed El Shahed's image  
Answer added by  Ahmed El Shahed, Engineering Group Supervisor, PGESCo
10 years ago

The answer below is correct but it is important to keep in mind that the condeser vacuum is imposed by the operating conditions. The minimum condeser pressure corresponds ... See More

Ahmed Aiada's image  
Answer added by  Ahmed Aiada, Senior Operator, kharafinational, kuwait
10 years ago

The first one is a title for start up the power plant after along time as the turbine is cool & our indication is the first stage temperature as actually it is less t ... See More

Ahmed Aiada's image  
Answer added by  Ahmed Aiada, Senior Operator, kharafinational, kuwait
10 years ago

The first one is a title for start up the power plant after along time as the turbine is cool & our indication is the first stage temperature as actually it is less t ... See More

Default profile image  
Answer added by  Anis Safi , planner projects, Enercon
8 years ago

Cold start is start the system without heating

Hussein galal's image  
Answer added by  Hussein galal, مهندس صيانة(تبريد وتكييف), cacker company for food industries
10 years ago

1-cooling water inlet temprature 2-loading on turbine 3- amount of air leakage