Trending PPAP Discussions

Follow

Ask the Community


Ask any professional question and get answers from other specialists.

Stream language
Badsha Khan's image
Question added by Badsha Khan Senior quality engineer IGW India limited
6 years ago
Answers:
14
Followers:
Views:
27
Vote Count:
0
Answer should contain a minimum of 25 characters.
MANSOOR ALI's image
Question added by MANSOOR ALI QA QC Engineer M/s Upshot Utilities Services Pvt Ltd
8 years ago
Answers:
1
Followers:
Views:
210
Vote Count:
0
Answer should contain a minimum of 25 characters.
Default profile image
Question added by Deleted user
9 years ago
Answers:
18
Followers:
Views:
234
Vote Count:
0
Answer should contain a minimum of 25 characters.
Nilesh Patil's image  
Answer added by  Nilesh Patil, Manager, Windals Precision Private Limited.
6 years ago

1) PPAP is applicable for production of new developed part /product. 2) For new supplier approval supplier evaluation / audit is applicable.

Anil Karale's image  
Answer added by  Anil Karale, Senior Engineer, John Deere
5 years ago

PPAP is a part of APQP , So if we go with APQP , PPAP automatically comes with it.

Mohammad Azam's image  
Answer added by  Mohammad Azam, Quality Engineer, Wintage Engineers & Consultant Pvt. Ltd.
5 years ago

Advanced Product Quality Planning

HUZAIFA PATEL's image  
Answer added by  HUZAIFA PATEL, Executive Assistant to General Manager, Azam Recruitment Sole Proprietorship LLC
6 years ago

APQP (advanced product quality planning) is a framework of procedures and techniques used to develop products in the industry, particularly the automotive industry.

HUZAIFA PATEL's image  
Answer added by  HUZAIFA PATEL, Executive Assistant to General Manager, Azam Recruitment Sole Proprietorship LLC
6 years ago

 PPAP helps manufacturers and suppliers communicate and approve production designs and processes before, during, and after manufacture.

Rakesh Ashabhai Patel's image  
Answer added by  Rakesh Ashabhai Patel, Field/Plant Coordinator Mechanical Engineer, QATAR SHELL PEARL GTL ON BRUNEL
6 years ago

To provide shortage materials, repair and service from outsource approved vendor, parts to increase euipment availibility for  continuous process plant and finally raise ... See More

Praveen Nathan's image  
Answer added by  Praveen Nathan, Senior Engineer , Roots industries India Pvt Ltd
6 years ago

APQP - Advance Production Quality Planning for Original Equipment Manufacturers will use to develop they’re products by studding from market needs and requirement to till ... See More