How can I load the management salaries to a project in primavera?

user-image
Question added by Tamer Mohamed , Contracts Representative , Saudi Electricity Company "SEC"
Date Posted: 2014/02/19
Owais A. Patel
by Owais A. Patel , Professional Services Manager , CMCS - Collaboration Management & Control Solutions

Create a resource with each of your Management individual and specify their Price/Unit. Then Assign them to various activities on your project with the estimated effort i.e. Budgeted Units.