Submitting more applications increases your chances of landing a job.

Here’s how busy the average job seeker was last month:

Opportunities viewed

Applications submitted

Keep exploring and applying to maximize your chances!

Looking for employers with a proven track record of hiring women?

Click here to explore opportunities now!
We Value Your Feedback

You are invited to participate in a survey designed to help researchers understand how best to match workers to the types of jobs they are searching for

Would You Be Likely to Participate?

If selected, we will contact you via email with further instructions and details about your participation.

You will receive a $7 payout for answering the survey.


Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

All of the following statements are true regarding the critical path method EXCEPT: ?

A. The critical path method performs a forward pass analysis and backward pass analysis through the project schedule network paths. B. Critical paths have either negative or zero total float C. On a network path, the schedule flexibility is measured by the difference between early and late dates D. The critical path method calculates the theoretical early start and finish dates for all schedule activities E. The critical path method accounts for resource limitations

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/06/19
Gaffar Elatta
by Gaffar Elatta , Project Manager , SOURCE for Development Co.

The critical path method accounts for resource limitations
لأن طريقة المسار الحرج (CPM) لا تأخذ قيود الموارد في الاعتبار، بل تحسب الجدول الزمني استنادًا فقط إلى تسلسل الأنشطة والعلاقات الزمنية بينها. إذا أردنا مراعاة الموارد، نستخدم تقنيات أخرى مثل Resource Leveling أو Resource-Constrained Scheduling.

andre andre
by andre andre , On Site Sitemanager/Structural /Civil/Mechanical/Tank plate Erection. , Kanye Kanye Projects Africa.

Critical path mesuerement used based on your Planning scope of work that are being carried out [Control System].

Dalia safey
by Dalia safey , nursing administration and staff development , Cairo University Hospitals

C. On a network path, the schedule flexibility is measured by the difference between early and late dates 

Athar Mohammed Khan
by Athar Mohammed Khan , Accountant , Integrated computer systems (ICS)

The critical path method (CPM) is a project modeling technique.

E. The critical path method accounts for resource limitations 

akhtar bebal
by akhtar bebal , Chief accountant /credit controller , Coca-cola

The critical path method (CPM) is an algorithm for scheduling a set of project activities. The critical path method (CPM) is a project modeling technique developed in the late 1950s by Morgan R. Walker of DuPont and James E. Kelley, Jr. of Remington Rand. Kelley and Walker related their memories of the development of CPM i

 

 

 

 

 

 

 

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

E. The critical path method accounts for resource limitations