Register now or log in to join your professional community.
A. The project is estimated to be- days ahead of schedule. B. Two branches converge on a node. C. The critical path must be evaluated to determine actual slack time. D. Duration compression may be required to meet the original project scope. E. None of the above.
D. Duration compression may be required to meet the original project scope.
Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.