Submitting more applications increases your chances of landing a job.

Here’s how busy the average job seeker was last month:

Opportunities viewed

Applications submitted

Keep exploring and applying to maximize your chances!

Looking for employers with a proven track record of hiring women?

Click here to explore opportunities now!
We Value Your Feedback

You are invited to participate in a survey designed to help researchers understand how best to match workers to the types of jobs they are searching for

Would You Be Likely to Participate?

If selected, we will contact you via email with further instructions and details about your participation.

You will receive a $7 payout for answering the survey.


Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You have been hired as a project manager for a local bank. Bank wants to develop and design the custom online bill pay software ?

so that its customer can pay bills online. You are ready to begin the activity duration estimates for your project. Two years ago you were involved in prior project where a team of ten programmers were able to create similar bill pay software in days. Therefore in estimating the duration of this new project, you decided to use days as an estimate. This is an example of which type of estimating technique? A. Qualitatively based duration B. Analogous estimating C. Reserve time D. Decomposition

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/05/08
Khaleelullah Syed Ibrahim Syed Ibrahim
by Khaleelullah Syed Ibrahim Syed Ibrahim , Resident Engineer , IDROESSE Infrastructures Middle East

Online Payment - Accept payment from anywhere, Fraud and Risk Management, Online pay gate way, Real Time Dash Board , Zero Security Deposit, Build IT with speedy integeration - Reserve Time 

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. Analogous estimating -------------------