You are a project manager for Bluebird Technologies. Bluebird writes custom billing applications for several industries. A schedule change has been?

requested. You know change is concerned with all of the following except which one?

A. Determining that a change occurred

B. Influencing causes of change

C. Verifying change

D. Managing change

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/10/13
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation: Integrated Change Control, Schedule Control, and Cost Control are all concerned with three issues: influencing the things that cause change, determining that change is needed or has happened, and managing the change.

يوسف دمدوم
by يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

 

Thank you for the detailed and useful answer

 

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.