In lump sum contract; if an item contradicts in BOQ and the Dwgs, knowing that the dwg will prevail,will the contractor take the BOQ rate or nothing?

user-image
Question added by mireille kirolos , Contracts and Claims Section Head , Egyptian Union for Construction-El Hazek
Date Posted: 2019/01/30
Mohammed Qaisar I PMP I MCIPS I MBA
by Mohammed Qaisar I PMP I MCIPS I MBA , Group Procurement Manager (Civil) , Al Ghurair Construction LLC

Lump sump contract also called fixed price contract. In this type of contract, the contractor is not entitled to any claim if there is a contradiction between BOQ and drawings. The contractor may take reference from specification/contract documents/general conditions to get clarity as all these documents take precedence over the drawing and BOQ. 