Most schedule simulations are based on some form of which of the following? a. Delphi b. PERT c. CPM d. Monte Carlo Analysis

user-image
Question added by Zakir Muhammed , Contract Administrator , DS Contracting Co.
Date Posted: 2018/05/30
Nicolas Aad
by Nicolas Aad , Warehouse manager , Bassoul & Heneine Group

 Monte Carlo is used most of the time.

Mohammed Qaisar I PMP I MCIPS I MBA
by Mohammed Qaisar I PMP I MCIPS I MBA , Group Procurement Manager (Civil) , Al Ghurair Construction LLC

It is nothing but Monte Carlo...

Bechir SEKRAFI
by Bechir SEKRAFI , Electrical engineering of the building , Ben Slama Electric

Most companies use  MS project Software which use the PERT program "technical evaluation and review programs" in their compilation

Abdullah Muhammad
by Abdullah Muhammad , Civil Engineer , Royal Marvelous Swimming Pools and Landscaping L.L.C

PERT is most scheduling technique is being used in these years

Paulina Corrales
by Paulina Corrales , Subcontracting Specialist , Bacao SAS

The most schedule simulation used is the Monte Carlo predictive analysis

Syed Salim
by Syed Salim , Senior Planning Engineer , Dar-Ul-Hindsaa

Monte Carlo Analysis is used for schedule simulations

M.N Sureshkumar
by M.N Sureshkumar , General Manager Construction , Century Contracting Co.LLC

Project Evaluation and Review Techniques

PRAVEEN ESWARA RAO
by PRAVEEN ESWARA RAO , Senior System Analyst , Dubai Municipality

Monte Carlo simulations are used to model the probability of different outcomes in a process that cannot easily be predicted due to the intervention of random variables. It is a technique used to understand the impact of risk and uncertainty in prediction and forecasting models

Muhammad Arfan
by Muhammad Arfan , Sr. Site Engineer , Elite Engineering (Pvt) Ltd.

Most schedule simulations are based on CPM

Zakir Muhammed
by Zakir Muhammed , Contract Administrator , DS Contracting Co.

Most schedule simulations are based on Monte Carlo Analysis