Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Pareto Analysis, cause and effect diagrams and flow charts are used in quality. A. Control. B. Assurances. C. Planning. D. Verification?

user-image
Question added by Richa Tiwari , Quantity Surveyor , Space Contracting Limited
Date Posted: 2018/05/24
Mohammed Qaisar I PMP I MCIPS I MBA
by Mohammed Qaisar I PMP I MCIPS I MBA , Group Procurement Manager (Civil) , Al Ghurair Construction LLC

In the light of PMI PMBOK it Pareto Analysis related to qualityy control.

Richa Tiwari
by Richa Tiwari , Quantity Surveyor , Space Contracting Limited

Pareto Analysis, cause and effect diagrams and flow charts are used in quality Control

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.