As a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is?

 A. Reduced.

B. Insignificant.

C. Doubled.

D. Increased.

E. Unchanged.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/01/11
Aneesh Shandilya
by Aneesh Shandilya , Manager/ Lead Electrical , Orpic

Option E - Unchanged is the correct answer.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

E. Unchanged. ---------------------