You work for a large manufacturing plant. You're working on a new project for an overseas product release. This is the company's first experience?

in the overseas market, and it wants to make a big splash with the introduction of this product. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the

A. The new machine, the concentrated formula, and the smaller package are all project constraints.

B. The new machine, the concentrated formula, and the smaller package are all considered deliverables.

C. The new machine, the concentrated formula, and the smaller package description must be incorporated into the product description document.

D. The new machine, the concentrated formula, and the smaller package are all project assumptions.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/12/07
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: BExplanation: Deliverables are tangible, verifiable outcomes or items that must be produced in order to complete the project or project phase. These items wouldn't be considered objectives, because the objective of the project is to break into the overseas market with a successful product revamped for that audience.

يوسف دمدوم
by يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation 

I agree the option C