You work for a large manufacturing plant. Your firm is thinking of initiating a new project to release an overseas product line. This is the?

company's first experience in the overseas market, and it wants to make a big splash with the introduction of this product. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the

A. The project manager should document the project's objectives and business justification in a project charter document and recommend that the project should proceed.

B. The project manager should document the business need for the project and recommend that a feasibility study be performed to determine viability of the project.

C. The project manager knows the project is a go and should document the project's objectives and known deliverables in a preliminary scope statement document.

D. The project manager should document the high-level product requirements and stakeholder

expectations in a preliminary scope statement.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/04/14
Alfayo Obam
by Alfayo Obam , Foreman , WILLIAMSON TEA (K) LTD

The project manager should document the business need for the project and recommend that a feasibilty study be performed to determine viabilty of the project. The reason being the company wants to come in a big way and not on trial basis. thus the companys vision and mission must be seen to be met by prepapring a very convincing document for adoption by the board.

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Most appropriate answer in my opinion is option B and thanks for the invite.

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

I seem option B is good answer..............................................

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion - B. The project manager should document the business need for the project and recommend that a feasibility study be performed to determine viability of the project.