Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

During what Time Management Process are the specific activities that must be performed to produce the deliverables in the WBS identified and?

 documented

A. Estimate Activity Duration

B. Define Activities

C. Sequence Activities

D. Develop Schedule

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/11/23
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. Define Activities -----------------

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.