Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Which of the following process takes the activities that are defined in the WBS and activity list, and accesses the amount ?

of time required to complete these activities? A. Schedule development B. Activity duration estimation C. Activity sequencing D. Activity definition

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/02/06
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. Activity duration estimation ----------

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.