In a cycle of project control , slack time refers to?

user-image
Question added by jonas ssemasaka , project manager , united mission board
Date Posted: 2017/10/06
kailas anande
by kailas anande , Senior Engineer Proposal and cost , Euro Mechanical

The amount of time that a schedule activity can be delayed

without delaying the early start of any immediately following

schedule activities.

Wael Al AAwar MBA PMP CPE
by Wael Al AAwar MBA PMP CPE , Project Controls Engineer , RA international

Slack is the amount of time that a task in a project network can be delayed without causing a delay to:

subsequent tasks ("free float")

project completion date ("total float") 

swamy kolagani
by swamy kolagani , Senior Planning Engineer , Khatib&Alami Engineering Consultants Pvt. Ltd

Slack Time refers to the amount of time the activity can be delayed without affecting the project completion Date

Karishma Ghosh
by Karishma Ghosh , Audit Assistant Manager , Ernst and Young LLP

It is the time a task can be delayed without affecting the project completion deadline.