Earned Value Analysis is used to measure performance based on the following parameters?

A. Scope and Cost B. Scope and Schedule C. Scope, Cost and Schedule D. Cost and Schedule

user-image
Question added by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology
Date Posted: 2017/06/22
Zulfiqar Ali Abro
by Zulfiqar Ali Abro , Lead Planner/ Scheduler , SNC Lavalin, Calgary Alber

It is Scope, Cost and Schedule.

ZULFIQAR ALI
by ZULFIQAR ALI , Project Controls Manager , Nakheel Dubai

The correct answer is C. Scope, Cost and Schedule

My understanding is that C is correct answer.

C. Scope, Cost and Schedule