Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

During progressing schedule P6 uses Retained logic, progress override and actual dates options used. When each option should be used?

user-image
Question added by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology
Date Posted: 2017/06/13
Zulfiqar Ali Abro
by Zulfiqar Ali Abro , Lead Planner/ Scheduler , SNC Lavalin, Calgary Alber

Retained Logic (RL): The retained logic schedule calculation setting holds schedule logic constant during calculation of in progress schedules.  The calculation adds activity remaining duration in the forward pass calculation for early dates and waits until activity predecessors are completed.

 

Progress Override (PO):  When the progress override schedule calcluation option setting is utilized, Oracle Primavera P6™ignores the predecessor activity relationships and calculates the activity completion date based on its own remaining duration.

  

Actual Dates (AD): When the actual dates schedule calcluation option setting is utilized, Oracle Primavera P6™sets the late finish date of the predecessor activity one day before the actual start of the out of sequence activity. This normally creates negative float to predecessor activities.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.