Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

The project schedule is used to determine all of the following except which one?

 A. Activity start dates

B. Cost estimates

C. Float times

D. Activity end dates

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/12/02
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: B

 Explanation: The project schedule determines the start and ending dates of activities, determines float times, generally shows resource assignments, and details the activity sequences and durations.

 

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.