Your project's primary constraint is quality. To make certain the project team members don't feel too pressed for time and to avoid schedule risk?

you decide to use which of the following activity

estimating tools?

A. Quantitatively based duration

B. Analogous estimating

C. Reserve analysis

D. Expert judgment

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/06/11
Hesham El Nasser
by Hesham El Nasser , Quality, R&D General Manager , Best of France for Dairy Product Co. Lactales Egypt Group {B.C.C}

Hi

I'm going to use  the Quantitatively based duration.

Since its gives flixability to mange which part need to put your stuff under stress, and not the all project - even they will understand piority, and will help to get your target in thim. 

Vishal  Lalwani
by Vishal Lalwani , Intern

Analogous estimating+reserve analysis

Stephen Scott
by Stephen Scott , IT Manager , Woolworths SA

I would use a blend of estimation tools based on the project environment, for example; quantitatively based duration is useful if you have a similar historic project or tasks to use as a baseline in addition to input from an expert in the either the project subject field, or in an expert field (e.g. Quality). 

Muhammad Aurangzeb
by Muhammad Aurangzeb , management , Muslim group of Componies

Quality always Depent at quantity at exp;judgement

KRISHAN MONGA
by KRISHAN MONGA , Superintending Engineer / Executive Engineer / Asst Executive Engineer , Corps of Engineers / MES

espert judgement is the need of the hour to assess the reasons for the quality constraints and to arrive at solutions to resolve the problems

Muhammad Dastgir Tabassum
by Muhammad Dastgir Tabassum , Assistant Manager , Bahria town

1) In my perspective, if any individual employee is not able to complete his/her role properly as per job description then you must find out the reason behind of it why his/her performance is not up to the level and the corective action should be taken immediatley that includes Training, Motivating etc. 2) Monthly/Quarterly/a half-year/Yearly Training plan (as convenient to your operation schedule) must be set for each employee by identifying training needs during PDR and cunducting refresh training session on important topic.

Iffat Jamil
by Iffat Jamil , Head of Programmes , Human Appeal

It depends on project, if big one and invloves too much indicators and integrated then combination of all would work, for small project Quantitaively based duration would work best.

Olivia Morfe
by Olivia Morfe , Human Resources & Training In Charge , Kingsgate Hotel Millennium & Copthorne

To make a certain project team I should Reserve analysis

Ricky Veniegas
by Ricky Veniegas , QC MECHANICAL ROTATING INSPECTOR , TECNICAS REUNIDAS-TR

 

D. Expert judgment

Provide problem solving for the team to help eliminate part shortages

PRASAD SAHASRABUDHE
by PRASAD SAHASRABUDHE , Accounts Receivable , UTC

In every business, Quality plays a vital importance. In order to maintain quality (either quality systems or product precision) it is better to make use of estimation tools and expert judgement to finalize duration, cost and product delivery.

 

Sayed saber Abdel aziz Ahmed
by Sayed saber Abdel aziz Ahmed , GIS Manager , Telecom Egypt

 

D. Expert judgmentD. Expert judgmentD. Expert judgmentD. Expert judgment