Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You have summarized the project and note that 28,000 hours have been scheduled, 25,000 hours have been earned and 26,000 hours paid?

The correct conclusion is:

A. The project is operating at a favorable cost efficiency ratio.

B. the project is spending more than planned

C. the project is behind schedule

D. the project is ahead of schedule

E. B and C

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/06/11
Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

I will go with option C - the project is behind schedule as shown by ZULFIQAR ALI and thanks for the invite. 

ZULFIQAR ALI
by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

SPI = EV/PV = 25000/28000 = 0.89. If SPI is less then 1 means project is behind the schedule.

My answer is C. the project is behind the schedule.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. the project is behind schedule

Reference:  Here, EV=25, PV=28 and AC=26; so CV = -1, SV = -3 and CPI = 0.96 and SPI = 0.89. Therefore it is over budget and behind schedule; but over-budget by very insignificant point, while it is certainly  behind schedule by over 10%. That's why answer is C.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.