Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You are a project manager for Star Light Strings. Star Light manufactures strings of lights for outdoor display. Its products range from simple?

light strings to elaborate lights with animal designs, bug designs, memorabilia, and so on. Your newest project requires a change. One of the business unit managers submitted a change through the change control system, which utilizes a CCB. Which of the following is true regarding the CCB?

A. The CCB requires all change requests in writing.

B. The CCB approves or denies change requests.

C. The CCB describes how change requests are managed.

D. The CCB requires updates to the appropriate management plan.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/04/07
Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

In my opinion option - B is most appropriate & thanks for the invite.

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you. I think answer is B. The CCB approves or denies change requests..

B. The CCB approves or denies change requests

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.