Whether the contractor is eligible for EOT and related cost claims due to the Employers or Engineers delays occurred ONLY for critical activities?

user-image
Question added by Alex Joseph , Deputy General Manager , RBDCK Ltd
Date Posted: 2017/03/22
ayaz ahmad
by ayaz ahmad , Contracts Manager , ABB

EOT PLUS associated cost can ONLY be granted if the delay to critical path activity(s) has been caused, Employer/Engineer.

In case of concurrent delay, the relief will depend on legal jurisdiction of the contract and/or expressed terms of the contract.