Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What to Include in your Cost Claims, So that it can be easily processed ?

user-image
Question added by Deleted user
Date Posted: 2017/03/08
Mohammad Abu Farha
by Mohammad Abu Farha , Cost Control and Subcontracts Administrator , OHL Industrial and MID Contracting JV

Cost plus method is the most easily processed  

Al Ameen Abbas
by Al Ameen Abbas , Quantity Surveyor Engineer , Copri Construction Enterprises Est.

While cost claims in the construction sector. Follows need to be added for easily processed.

1. Bill of Quantities.

2. Price variation orders (If any).

3. Inspection report which approved by consultant or client (to identify work done activities).

4. Approved IFC drawings and shop drawings.

 

 

5. To claim variation / additional works, need to be include variation order issued by consultant or client along with inspection report of those works (inspection report required to know work done activities)

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.