During the planning phase of a project, you realize that more than one functional department possesses the skill and technical know-how to?

 

perform a given task.The best way for the project manager to handle this would be to:

A. Allow each line group to perform part of the task

B. Make the decision, document it in the linear responsibility chart, and distribute the chart to all departments.

C. Ask the executive sponsor to make the decision

D. All of the other alternatives apply

E. Let the affected line groups decide among themselves who will perform the work

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/03/03
ZULFIQAR ALI
by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

It is very tricky question. As far as my knowlege the answer is 

E . Let the affected line groups decide among themsleves who will perform the work

Sattar Abdulkarim  Mohamed
by Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

The correct Answer is Option E.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion

E. Let the affected line groups decide among themselves who will perform the work

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. My opinion is option E.

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Under the given circumstances , I will go with option  C .

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is B

B. Make the decision, document it in the linear responsibility chart, and distribute the chart to all departments.