Activities with zero time duration are referred to as?

 

A. Noncritical path activities.

B. Critical pathactivites.

C. None of the other alternatives apply.

D. Slack time activities.

E. Dummies

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/02/24
hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

 

Option E

 

Ahmad Mohammed
by Ahmad Mohammed , Project Manager , ReachIT Solutions

C. Slack Time Activities as in Project Management the amount of time is called float or slack.

Nadjib RABAHI
by Nadjib RABAHI , Freelancer , My own account

Option - B :  Critical pathactivites.

 

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. I seem option E. Dummies is good answer.

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

I will go with option C ; I do not think PMI uses the term dummies.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion - E. Dummies

Sumaiyah Bhatti
by Sumaiyah Bhatti , Account Manager , ALTAVIA GROUP - MARKETING SERVICES PARTNER

they are called Slack Time Activities 