Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Together with your team, you applied three-point estimation on a Critical path which consists of two activities. The following duration ?

uncertainties are all calculated assuming a ±3sigma Confidence interval. The duration uncertainty-defined as pessimistic minus optimistic estimate-of the first activity is days; the second estimate has an uncertainty of days. Applying the PERT formula, what is the duration uncertainty of the entire path? A. No statement is possible from the information given. B. days C. days D. days

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/10/03
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. 30 days --------------------

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.