Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

In crashing a task, what would you would focus on?

 

A. Accelerate performance by minimizing cost.

B. As many tasks as possible and accelerate performance by minimizing cost.

C. Non critical tasks.

D. Accelerating performance of tasks on critical path.

E. As many tasks as possible.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/01/21
Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Out of the given , option D appears to be most appropriate.

hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thanks for invitation

Option D

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.