In time-cost optimization of a project, crashing is done.

A) On all the activities

B) On all the activities lying on the critical path

C) Only on activities lying on the original critical path and having flatter cost slopes

D)On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

user-image
Question added by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia
Date Posted: 2016/08/08
ehab abu zaid
by ehab abu zaid , civil engineer , Manwa trading and contracting company

I think the answer is ( C ) .