Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

The project manager develops a process improvement plan to encourage continuous process improvement during the life of the project. (cont.)

 technique to assist the project manager to assure the success of the process

improvement plan?

A. Change control system

B. Process analysis

C. Benchmarking

D. Configuration management system 

user-image
Question added by Nader Ali , Technical office manager , AlSafwa Contracting
Date Posted: 2016/09/20
bedan Ian
by bedan Ian , Food service worker , Kenya Serena Hotel

PMP: Project Management Professional. ... CAPM: Certified Associate in Project Management. ... CSM: Certified ScrumMaster. ... CompTIA Project+ certification. ... PRINCE2 Foundation/PRINCE2 Practitioner. ... CPMP: Certified Project Management Practitioner. ... APM: Associate in Project Management

Hany Farahat Mohamed Ahmed
by Hany Farahat Mohamed Ahmed , MEP Project Manager , LEEDS

B. Process analysis to improvment plan 

Mohamed Ahmed Badie Mohamed Abdalla
by Mohamed Ahmed Badie Mohamed Abdalla , Digital Transformation (DT) Portfolio Manager , Confidential

Process Analysis would be the best available technique to monitor and evaluate the improvement applied.

d configuration management system( project exists after surving a principle)

Writing an essay is a unique form of expression that allows individuals to delve into their thoughts and ideas. It is a structured piece of writing where one can articulate opinions, analyze concepts, and present arguments. Essays encourage critical https://www.phdresearch.net/ thinking, creativity, and effective communication. Whether exploring literature, science, or personal experiences, the essay is a versatile platform for conveying thoughts and making a lasting impact through the power of words.

Ksenija Kancelak
by Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

My answer is: B. Process analysis

Imran Ahmed
by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-B Process analysis..................................

Nader Ali
by Nader Ali , Technical office manager , AlSafwa Contracting

ANSWER (B) Process Analysis IS CORRECT

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

I think  B is appropriate option