You are in process of exterminating which set of project activities will take the longest to complete? See below for detail

Which of the following is the MOST appropriate tool to use?

A. RBS

B. Gantt chart

C. WBS

D. Milestone chart

E. Network diagram

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/08/20
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The most appropriate option is

E. Network diagram

A Gantt chart, commonly used in project management, is one of the most popular and useful ways of showing activities (tasks or events) displayed against time. 