Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Why are most of construction projects not completed within contract duration of the project in gulf countries?

user-image
Question added by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia
Date Posted: 2016/08/01
Jasim Kooriparambil
by Jasim Kooriparambil , Project Civil Engineer , DAR CONSULTING ENGINEERS

There are many reasons:

1. Improper Planning.

2. Resources.

3. Improper Managment.

4. Harsh climate.

5. Material Shortage.

6. Budget deficiency

 

zakaria karime
by zakaria karime , civil project engineer , Federici Stirling Batco

during the tender , estimation for the duration of the project is based on competition between the contractors , which making them choose a minimum duration to win the tender without considering all the obstacles that could be faced, like utilities ( High voltage cables - telephone cables ...) , Petrol Lines...etc , and specially in the gulf area , it takes too much times to get approval for relocation or protection of any of those utilities , sometimes it takes 1 year to get approval. and there are also other problems like consultant problem, modification of design, accidents ... but again the main problem is the big delay in the completion of any approval or NOC in the Government departments.

Adam Forster
by Adam Forster , Group OHSE Manager - Australia , Wabtec Pty Ltd

 

I feel that the majority of construction projects not completed within contract duration of the project in gulf countries? Comes down to Lack of knowledge in Risk analysis and Implementation, these risks in gulf countries are not unlike projects in other countries or remote locations)

 

Procurement Process - Most of the major materials have to be outsourced the country (this can be mitigated by planning lead times into the delivery schedule)

 

Unrealistic schedule (this is managed / planned out by the scope phase of the project, (a skilled negotiator should be able to communicate to the client if their plans are unrealistic or unachievable)

 

Poor Resource management - especially in deployment of Skilled and Qualified personnel (Planning risks and lead times for ramp up of manning in a manning schedule should reflect realistic objectives).

 

Climatic condition (again Planning risks, these are known and specifically legislated by KSA, so need to be reflected in the works schedule)

 

Poor labour welfare - affects employee Production (these are known risks specifically legislated by KSA, so need to be reflected in the works schedule)

 

Poor management (a clear scope, selection criteria, and rigorous assessment of candidates that best suit the position can also mitigate these risks)

Rajasekar Subramanian PMP MMUP Certified
by Rajasekar Subramanian PMP MMUP Certified , Sr.Planning Engineer , Al Darwish Engineering W L L

There many casue and factors are contribut in Project Completion in Gulf contries

1) Prourement Process  - Most of the major material have to out source the contry

2) Un realistc schedule 

3) Poor Resourse management  - especaily in deployment of Skilled and Qualified 

4) Climatic condition 

5) Poor labour welfare - Which affects their Production

6) Poor management 

7) Lack of knowledge in Risk analysis and Implemention 

 

Few reasons are; 1.un qualified managers 2.Budget deficiency 3.undefine SOW 4.staff doing multiple roles or under staff. 5.additional works or variations.

Hesham Mugharbil
by Hesham Mugharbil , General Manager Gm , First Level Trading Co

I would say that this is not specific to a certain country or region, but varies from company to company and sector to sector (private vs. public). The main issues might include lack of project management skills, especially lack of monitoring and control and risk management. Also, regarding budget, sometimes contractors don't get paid on time and end up with major delays.

Mousab Al Nokkari
by Mousab Al Nokkari , Engineering Manager , Al Majaz Engineering Consulting Office

 

Thanks for invitation ,,

 

1. Lack of Agreed Requirements, Resources.

 

2. Lack of Proper Project Planning.  

 

3. Poor or Lack of Proper Change Control. 

 

4. Inadequate Cost Control .

 

5. No Agreed Development Process.

 

6. Poor Communication. 

 

7. Lack of Focus, Supervision, Overseen. 

 

8. Lack of Commitment.

 

9. Manpower turnover.

 

10. The abnormal Climate & Weather.

 

With Best Regards

Ahmed Taha
by Ahmed Taha , Digital Director , Home of Performance

I beleive this is due to many elements such as:

1- delay in Legal documentations

2- Delay in funding 

over all, timeline is Gulf is not really respected 100% 

Shiva Gadepalli
by Shiva Gadepalli , Lead Consultant , A & A Business Consulting Pvt Ltd

In the Gulf, major reason is the attitude of the management and haphazard thinking process of the decision makers. No responsible individual has the right to act on professional lines, irrespective of the realities. This is the major cause for delays in any project.

Ahmed Hassan
by Ahmed Hassan , Service Delivery Manager , Goodnews4me

There are many factors for the delay

Labor-related factors

Contractor-related factors

Project-related factors

Owner-related factors

Consultant-related factors

Plan/equipment-related

Design team-related factors

Materials-related factors

External factors

Ahilan R
by Ahilan R , Scientific Assistant-D , Nuclear Power Corporation of India Ltd (NPCIL)

Undefined scope & lack in management 

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.