The critical activity has_.

A.     maximum float

B.     minimum float

C.     zero float

D.     none of these.

user-image
Question added by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL
Date Posted: 2016/04/27

Critical activity have no total or free float . 

also the early and late start are the same .

Mohamed Helal
by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

The correct answer is....C. zero float

sardar mardookhy
by sardar mardookhy , PMP certified Project manager , MCCI

"C" zero float 

the critical activity should be finished in time 

Ahmed Mohamed Ayesh Sarkhi
by Ahmed Mohamed Ayesh Sarkhi , Shared Services Supervisor , Saudi Musheera Co. Ltd.

my answer is option " c "           .

georgei assi
by georgei assi , مدير حسابات , المجموعة السورية

The correct answer is d ..............

Eng Ahmed Elsharkawy
by Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,,

my choice is option d 

mohammed negm
by mohammed negm , مدير مبيعات , مؤسسة أطياف لتجارة المواد الغذائية

i agree the experts  answers d 

Yahia mohamed  Amen Gad
by Yahia mohamed Amen Gad , إدارة - مدرب - , سنابل الأجيال للتعليم والتدريب

Thank you for your call / a

mohamed abd el hamid abd alla elfarran elfaran
by mohamed abd el hamid abd alla elfarran elfaran , مهندس مدنى , مكتب العطيشان الهندسى

THANKS FOR INVI TI ON    ANSWER IS D

ghazi Almahadeen
by ghazi Almahadeen , Project Facilitator , Jordan River Foundation

Thanks for the invite ......................... A. maximum float

Omar Saad Ibrahem Alhamadani
by Omar Saad Ibrahem Alhamadani , Snr. HR & Finance Officer , Sarri Zawetta Company

Thanks

It is (D)...................................................