Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What percent of the takt time should be used to calculate number of resources for ideal loading?

user-image
Question added by jyoti rm
Date Posted: 2016/01/04

   

time should be used to calculate number of resources for ideal loading is7 minutes

عبد الهادي طخيس
by عبد الهادي طخيس , عامل , MADEP

“Cycle time” can mean the total elapsed time between when a customer places an order and when he receives it. This definition can be used externally, or with internal customers. This definition actually pre-dates most of the English publications about the Toyota Production System.

It can also express the dock-to-dock flow time of the entire process, or some other linear segment of the flow. The value stream mapping in Learning to See calls this “production lead time” but some people call the same thing “cycle time

asif Nazir
by asif Nazir , Production Manager , Khyber Chemical (Pvt.) Ltd.

Available Minutes for Production / Required Units of Production = Takt Time

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.