Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What are the key responsibilities of hvac site engineer?

user-image
Question added by PRAVEEN DAVID
Date Posted: 2015/10/16

 

 

 

  1. Get approved HVAC Shop Drawings, MEP- Coordination Drawings, Work method statement and Project Specification from Project Engineer.

  2. Ensure the HVAC Ducts, Fittings, accessories and Child water pipes, fittings, accessories  are available and approved by Inspection department  prior to installation

  3. Ensure sufficient hand tools, power tools, ladder and scaffolding are available for installation

  4. Coordinate with other discipline and ensure  site clearance is available to start the HVAC Activities

  5. Arrange the sufficient manpower such as Supervisor, Foreman, Duct fitter, pipe fitter, Assistant duct and pipe fitter etc.., and ensure all of them attended safety orientation and having proper PPE’s prior start installation activities at site

  6. Provide approved HVAC Shop drawing, MEP Co-ordination Drawing to site supervisor (or) Foreman and inform them to shift the required ducting and piping approved material from warehouse to site and arrange required material to avoid progress delay.

  7. Prior to start HVAC activities notify to QC Personal for surveillance to ensure the quality work

     

  8. To maintain safe all construction  HVAC  and Chilled water piping activities are carried out in accordance with the Company’s safety policies and procedures; ensure that appropriate safety and protective equipment is used by Company & Contractor staff.

     

  9. Closely monitor site activities to ensure quality of work is in compliance with approved shop drawing and Specification and get daily progress report from site supervisor (or) foreman and update to project Engineer (or) Manager

     

  10. Preparing relevant documents to conduct inspection for completed installation activities and raise RFI to QC-Inspector (To ensure that any activity offered for inspection has an attachment of IFC drawing, method statement (if required), Inspection & Test Plan (ITP) followed by check list)

     

  11. Carry out all planned site inspections as per the intervention points marked in the relevant drawing and standard

     

  12. Preparing the relevant documents to Conduct Testing inspection such as Duct light testing for Ducts and Hydro test for Above ground and Underground chilled water piping’s, systems.

  13. Active involvement in weekly meetings with the Project management & QC Supervisor and manager to resolve the site related issues.

  14. Assist the Commissioning Team in Pre-commissioning & Commissioning stages of all HVAC Equipment’s.

  15. Assist the Commissioning Team on Testing, Adjusting & Balancing (TAB) stages of the Air and Hydronic Piping’s.

   

             . Assist the Project Engineer during Preparation of final Test Reports, as built drawings, Operation & Maintenance manual and handing over the project to client

 

Mahmoud Badr
by Mahmoud Badr , Sr. Mechanical Site Consultant Engineer , EHAF

1-Site supervision.

2-Site Work Inspection as per approved shop drawing

3-Material inspection as per approved material submittal

4-Work Follow up as per approved progress

5-Daily progress report.  

6-FOR and NCR of complete Mechanical works

Muhammad Arsalan Siddiqui
by Muhammad Arsalan Siddiqui , MEP Project Manager , JLL

Review the design

verify the load calculations

check the shop drawings

check the material submittal

check the method statement for installation 

check the site work and material delivery

testing commissioning with approved vendors

as built drawings ans O&M Manual

Nasar Iqbal
by Nasar Iqbal , Civil instructer , I.U.S.E School of Technical Education Rawalpindi

see on daily motion interview of Engineers

 

Nihal Mukadam
by Nihal Mukadam , Mechanical Inspector , Parsons - Qatar

1. Coordinating Duct/Pipe routing with site conditions & other services.

2. placing correct order for duct fabrication.

3. maintaining quality checks for installation

4. leading & improving skills of team of Sub-ordinate Supervisors/foreman

SITE SUPERVISING OF WORKRES

MATERIAL INSPECTION

DAILY PROGRESS REPORT

mohsinuddin mohsin
by mohsinuddin mohsin , mechanical engineer , power solutions

thumb rule

drawings

working according to drawings

material availabilty for work

work done report for the work

Hassan Ahmed Fawaz  Rashwan
by Hassan Ahmed Fawaz Rashwan , startup and operation engineer of thermal power plant , Egyptian Electricity Holdind Company

good knlowdge and uderstandind of hvac shop drawings as duct system and P&IDs. is the main key responsibilities of hvac engineer.

Farzad Rooholamin
by Farzad Rooholamin , Mechanical Maintenance Engineer , Milad hospital

Accuracy, strong vision, examining problems and providing solutions

Anil Jain
by Anil Jain , ATS Infrastrucure Ltd

To ensure the site work is executed inline with approved shop drawings, technical specifications within the schedule.

Mohammed Ahmed Pasha
by Mohammed Ahmed Pasha , Mechanical Project Engineer , Innovative Contractors for Advanced Dimensions

1. Firstly they take the safety measures 

2. celearence on site 

3.Work permit for using any fabrication Work on site

Example: welding works through which the chances tom get fire and Ect.

4.Inspection of meterial as per the BOQ 

5.Quatity should not Exceed the BOQ 

6.Regularly meetings with client and reporting to the project Coordinator or Concern Depertament 

7.Taking care of our tools and materials.

finally they are so many things but its depend on type of project and all..

 

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.