What is acceptance time to remove the roof shuttering area 144 sq.m and temp 35 degree Celsius?

user-image
Question added by Matloob Ahmad
Date Posted: 2015/10/07
Hanna Sleman
by Hanna Sleman , Project Engineer , Dubai Trust Contracting (L.L.C)

acceptance time to remove the roof shuttering area 144 sq.m and temp 35 degree Celsius is 21 Days