Submitting more applications increases your chances of landing a job.

Here’s how busy the average job seeker was last month:

Opportunities viewed

Applications submitted

Keep exploring and applying to maximize your chances!

Looking for employers with a proven track record of hiring women?

Click here to explore opportunities now!
We Value Your Feedback

You are invited to participate in a survey designed to help researchers understand how best to match workers to the types of jobs they are searching for

Would You Be Likely to Participate?

If selected, we will contact you via email with further instructions and details about your participation.

You will receive a $7 payout for answering the survey.


Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

The Gantt Chart visually shows when tasks are supposed to be done and compares that with the

(a)

Scheduled delivery of materials

(b)

Supervisor’s estimate of completion

(c)

Customers’ requested date of delivery 

(d)

Actual progress on each task

(e)

Scheduled release of future orders.

 

user-image
Question added by Vinod Jetley , Assistant General Manager , State Bank of India
Date Posted: 2015/04/24
Vinod Jetley
by Vinod Jetley , Assistant General Manager , State Bank of India

(d)The Gantt chart visually shows when tasks are supposed to be done and compares that with the actual progress on each. Hence, option (d) is correct.

FITAH MOHAMED
by FITAH MOHAMED , Financial Manager , FUEL AND ENERGY CO for transportion petroleum materials

d)>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

Actual progress on each task

Wasi Rahman Sheikh
by Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG

Option <<<<<<<<<<<<<d) <<<<