Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

In the first six month update on a 1 year, $100,000 project, the analysis shows that the BCWS is $50,000; the BCWP is $40,000 and the ACWP is $30,000.

What can be determined from these figures? 

 

A. The project is behind schedule and over cost.B. The project is ahead of schedule and under cost.C. The project is ahead of schedule and over cost.D. The project is behind schedule and under cost.

user-image
Question added by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
Date Posted: 2015/01/19
Mohamed Galal Hussein Ahmed Mohamed
by Mohamed Galal Hussein Ahmed Mohamed , Technical Mnager , Fast Building Contracting Co.

 

 

SchedulePerformanceIndexSPI =BCWP/BCWS=40000/50000=0.8<1

 

CostPerformanceIndexCPI= CWP/ACWP=40000/30000=1.33>1

Then the answer is D

 

 

 

 

 

 

 

 

 

 

 

 

 

SchedulePerformanceIndexSPI =BCWP/BCWS=40000/50000=0.8<1

 

Wolf Klaas Kinsbergen
by Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

For me answer A

mohamed sabry hassan
by mohamed sabry hassan , accountant , target group

answer d

RAJ DAHIYA
by RAJ DAHIYA , Senior MEP Projects Manager , Trinity Engineering Services L.L.C.

_______________________________________________________________

D. The project is behind schedule and under cost.

_______________________________________________________________

Alex Al Yazouri
by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

Yes, the correct answer is

D. The project is behind schedule and under cost.

 

CPI = EV/ AC = 40000/30000  = 1.333  > 1  ===> Below budget.  GOOD

SPI = EV/ PV = 40000/50000  =  .8  < 1   ===> Behind schedule.  NOT GOOD

 

              

Irina Chepel
by Irina Chepel , Personal trainer , Freelancer

It's not exactly my field of the expertise

Muhammad samran
by Muhammad samran , Junior Officer/Project Coordinator , Pakistan Stell Mill

the answer is D

Divyesh Patel
by Divyesh Patel , Assistant Professional Officer- Treasury , City Of Cape Town

I will go with answers given by experts.

hachem hadjira hachem hadjira
by hachem hadjira hachem hadjira , مسؤولة مصلحة بالكلية لحاملي الشهادات ورئيس,التعليم التقييم ،سيرت مكتب شؤون إجتماعية.مكلفة بالمخابر , جامعة العقيد أحمد دراية ولاية أدرار

D. The project is behind schedule and under cost

but i dont now a comtability 

and thinks for your invitation

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.