Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Any audit recommendation when to close in system ? After actual implementation or when it is set for approval in system ?

user-image
Question added by Amod Mohite , SAFETY OFFICER / ENGG , Reliance Industries Ltd
Date Posted: 2015/01/05
Ankit Hariyani
by Ankit Hariyani , Manager - IT Infrastructure Operations & Service Delivery , Cognizant

Only after actual implementation as every corrective action needs to be compeletely implemented before any RCA gets closed in system.

Hafiz Abid Ali
by Hafiz Abid Ali , OPERATION ENGINEER , Saudi Arabian Fertilizer Company (SABIC Affiliate)

After actual implementation because if we close the reccommendation after raising MOC/TSR and it is dropped during study so there is no use to do RCA. So closure should be after actual implementation or dropping of recommendation.

Noel Cezar
by Noel Cezar , MANAGER , JANNET MERCHANDISING

As part of a corporate quality management system, an action item may be closed upon implementation of any corrective action. An audit is useful, i.e., effective, when the corrective action is assessed against a performance indicator or baseline. 

Naveed Mohammed
by Naveed Mohammed , Manager , Capgemini India Limited

At the beginning you need to have a blueprint of the servers ,where you can start implementing the system before you take it forward to production and once it is done it should move to Non Production Phase and then to Production after performing sanity checks , then you can conclude with UAT user acceptance test and release the system to business .

Sreekanth Varrier
by Sreekanth Varrier , IT Process Manager , Shell

Audit comments should be closed only after the actual implimentation.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.