Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

How can i calculate the manpower of a factory?

user-image
Question added by Hosam Mohamed Abd Elhameed Farghaly Helal , Technical Sales Engineer , Gulf Gasket Factory
Date Posted: 2014/12/24
ched oliverio
by ched oliverio , Accountant , Freelance

First identify your plant capacity,counter it against your production requirement,

such that if plant capacity > production req take production requirement else take capacity.

Then identify all activities related to your plants operation,set the standard efficiency for each operation. Identify how many hours would you wish the plant to operate and follow this simple formula 

 

Plant Capacity or Production Req / (Operating Hours x Efficiency) = Manpower Requirement ;)

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.