Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

A project manager discovers that a project problem has occurred.

<h3>The problem was never discussed during risk planning activities or added to the risk register, and it will now cost the project money. What is the BEST response?</h3>

user-image
Question added by Deleted user
Date Posted: 2014/12/04
Omair Abduljaleel Ali Al-Quliey
by Omair Abduljaleel Ali Al-Quliey , مدير لمكتب المهندسين اليمنيين , مكتبي مكتب المهندسين اليمنيين

Thank you for invitation >>>

with answer of Ayoub Tartir and i will add this: if some risks don't happen and will not happen at futur in the risk registers, the solution to take their costs to this new risk which not in risk logs>> 

Need to hold an immediate meeting with the project sponsor/senior management to discuss this issue and look for a best risk-based and cost effectiveness solution. In other words, the project should not be closed down, except if the sponsor approved to close it.

Samuel Trapp
by Samuel Trapp , Contract Manager, Business Consultant, General Counsel , TGC

I agree with Mr. Bosman and Mr. Al Yazouri. To those answers I would add that the contract needs to be reviewed as well. Provisions likely were addressed (or at least should have been) in the contract itself as to the procedure in the event of force majeure or unforeseen circumstances.  Proper Planning Prevents Poor Performance!  Realize that you need to plan ahead at the contract phase for unexpected problems.  They can and do occur.

Alex Al Yazouri
by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

Call for a meeting between concern parties, explain, open a claim with project control manager and investigate to find out whose responsibility is it, and go from there.

Amer Alokeh
by Amer Alokeh , Service Delivery Manager , SmartWorld DWC LLC

We need to assess  the occurred problem to look for the quantified impact on project constraints. So we know what Extras are needed!

As said, The risk was not really identified. So the risk is Unknown and funds can be requested from Management Reserves after Board approval. 

However, If the risk occurred by misplanning or lack in knowledge of PM, I recommend the below response.

If the risk management process were ideal and driven perfectly. I assume some risks were closed in previous stages that can accommodate the cost of the new occurred risk. 

Hossam Maghrabi
by Hossam Maghrabi , Project management & BPM Consultant. , Freelancer

This an “unknown-unknown” risk type so you have to use a management reserve to manage its impact after management approval.

for more details please have a look on the following article,

http://pmstudycircle.com/2012/02/contingency-reserve-vs-management-reserve/

 

Hope this can help

 

  

Sarfaraz Ahmed
by Sarfaraz Ahmed , Executive/Project Engineer , Quaid-e-Awam University Engineering Science & Technology

The project Manager will go to the organizational process asset library and finds a Work Break Down Structure.

فؤاد أحمد حسين
by فؤاد أحمد حسين , مدير , حكومي

Thank you my brother about your invitation ,,, It is known that the implementation of civil engineering construction contracts being drafted based on the general conditions for the implementation of contracting civil engineering and I do not know how different paragraphs of those terms between one country to another, and in all cases must Resident Engineer to act on the basis of the powers conferred upon him under those established on the basis of the contract formula, and for me I will answer based on the conditions of public two sections I and II in my,,, Article52 and Article53 of the General Terms cover the case of the question, where has the right to make changes and calculating the value of changes in certain limits up to20% conditions the increase and decrease of the quantities contained in the table quantities calorimeter based as stated in the articles above.

Mohamed Sulaiman
by Mohamed Sulaiman , Site Project Manager , Al tabarak for Engineering & Contracting company

Project Manager should discuss the problem with the concern parties and try to take a decision as soon as possible to solve the problem without any delay in project schedule, PM should be proactive and have ability to control extra cost for the problem.

Muhammad Khalil
by Muhammad Khalil , Chief Engineer (Civil) , Water and Sanitation Services Mardan

Thank you for invitation Dear brother. Actually in most of the project unforeseen cost are taken into consideration with some percentage to the project cost and that is considered during time of approval of the project. But if that is not included during time of approval then meeting should be arranged with all stake holders for the solution of the problem.

Leon Bosman
by Leon Bosman , Manager - Special Projects , De Beers Marine

The first step would be to call the project members together immediately to assess the risk in depth. this will be to quantify the oversight but more importantly to establish what other risks might come in to play. Remedial actions need to be formulated as soon as possible and after this the risk must be re-evaluated. Only after this would I would I approach my management. The worst thing that I believe is that people tend to overreact rather first doing due diligence to problems before reporting such. Go to your manager with the problem but make sure that you have suggested remedial actions, otherwise it will be viewed that you passing 'the preverbual monkey'. To continuously revisiting the risks and to rank them with probabilities and additional remedial actions with your team is a must! Risks are a fact of life but remedial actions taken is what differentiates a good project manager.    

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.