ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Consider the project integration management knowledge area. Which of the following process are NOT included?

A. Integrated change control B. Develop project management plan C. Develop preliminary project scope statement D. Direct and manage execution E. None of the choices are true

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2019/01/09
Mohammed shahvali shaik
من قبل Mohammed shahvali shaik , IT Manager , ARIG

All given process are included because point C is tricky because if we remove word prelimanary then Project scope statement is actually under Develop project management plan process. 

abdulla shutnawy
من قبل abdulla shutnawy , Security Manager , nokia

Seven processes of project integration management :

Develop the project charter.

 Develop the project management plan.

Direct and manage project work.

monitor and control project work

perform integrated control

close project or phase

so I said C is not included in the integration managment

 

 

Harish Verma
من قبل Harish Verma

Project Integration Management starts with developing Project Charter, then Develop Project Management Plan, Direct and Manage Project work, Manage Poject Knowledge, Monitor and Control Project work and Perform Integrated Change Control Process and the finally Close Project or Phase.

Option C is correct answer, there is no as such developement of Scope statement.

Nasiru Sani Ango
من قبل Nasiru Sani Ango , monitoring and inspection , National youth service corps

E-None But implementing Business process Improvement

ahmed Fouad khalil Khalil
من قبل ahmed Fouad khalil Khalil , Senior project engineer , Advanced Line Group (Construction)

C-Develop preliminary project scope statement 

is not included the correct is to develop a project charter,

The scope statement is part of the project plan 

othman othman
من قبل othman othman

All are included. A & D fall under integrationB & C fall under Scope ManagementWhich are all required.

Binu Thomas
من قبل Binu Thomas , Camp Manager , Hospitality Catering LLC

E. None of the choices are true

Mohammad Alshokan
من قبل Mohammad Alshokan , Project Engineer , Saudi Aramco

C. Develop preliminary project scope statement

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. Integrated change control --------------------

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟