ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

You are in the process of controlling changes to the project cost baseline. What is the LEAST helpful tool/ technique?

A. Performance measurement analysis B. Forecasting, variance management C. Cost change control system D. Cost aggregation E. Project performance reviews

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2019/01/02
MURAT MIDIK
من قبل MURAT MIDIK , SAP Project Manager , Spectrum Consulting

Correct Answer is D.:Cost aggregation

z dawaliebi
من قبل z dawaliebi , مدير مالي واداري , wataniah

I think Cost aggregating, through project management, using the tool of Control Estimates, will be the least, plus other choices available.

Oscar Jr Alisen
من قبل Oscar Jr Alisen , Senior Accountant , OVERSEAS MARINE LOGISTICS LLC

D. Cost aggregation - all other choices are helpful tool/ technique in the process.

Arvind Kumar Yadav
من قبل Arvind Kumar Yadav , Assistant Manager Technical , Aristocrat India pvt Ltd

D. Cost aggregation

ALI MOHAMED IBRAHEM BENHAYA
من قبل ALI MOHAMED IBRAHEM BENHAYA , مدير مكتب البعد الرابع 4DD , FOURTH DIMENISION ENGINEERING & CONSTRUCTION

 THE ANSWER

D. Cost aggregation

alaa kamal
من قبل alaa kamal , QUANTITY SURVEYOR ENGINEER , HAMAD AL-SAGHYIR COMPANY

D. Cost aggregation  ........

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. Cost aggregation ------------------

Boumediene BENRAHAL
من قبل Boumediene BENRAHAL , Enseignant economie energetique , ESE (Ecole supérieure d’Économie UNIVERSITÉ D'Oran

C COST CHANGE CONTROL SYSTEM

Muhammad Usman Khakwani
من قبل Muhammad Usman Khakwani , Planning and Reporting Manager , Tunn3l Jv

The least one tool or technique for cost controller is (B.) Forecasting and Variance Management. Variance calculation provides knowledge of overspending of major KPI´s with respect to the cost baseline. Moreover, the forecasting allows management to know the impact on the overall project and initiate thoughts for the mitigation and recovery measurements. 

HARESH KUMAR DARJI
من قبل HARESH KUMAR DARJI , Freelance Finance & Business Management , Upyog Technology Pvt Ltd

D. Cost Aggregation.....................

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟