Which of the following actions is an example of risk response?

 A. reduce the consequences of potential project risk events

B. wait until a problem actually happens, then deal with it in the most effective and efficient manner.

C.1) adjust project parameters (scope, time, quality ...),2) reduce the probability of potential project risk events,and reduce the consequences of potential project risk events.

D. reduce the probability of potential project risk events E. adjust project parameters (scope, time, quality ...)

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/01/04
Zaferullah Sharief, PMP®
من قبل Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

option C is the best choice.

Leslie Petersen
من قبل Leslie Petersen

C.1) adjust project parameters (scope, time, quality ...),2) reduce the probability of potential project risk events,and reduce the consequences of potential project risk events.