ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

How you can minimise your transit cost and decrease latency?

user-image
تم إضافة السؤال من قبل Mirza Ahmer Baig , Network Engineer , DE-CIX Management GmbH & UAE-IX Dubai
تاريخ النشر: 2017/11/26
Ain ul Hayat Soomro
من قبل Ain ul Hayat Soomro , Structural Design Engineer , Al Jazirah Engineers & Consultant (PMC)

We can minimize it by applying the Project Crashing Method where Crashing is a schedule compression technique used to reduce or shorten the project schedule.

The PM can various measures to accomplish this goal. Some of the common methods used are,

1-Adding additional resources to the critical path tasks:This option has various constraints such as the securing of the budget to add the resources, and the availability of the resources.

2-Reduce the project requirements or scope:This can be done only if the sponsor and major stakeholders agree to reduce the scope

After applying the crashing, the critical path might have changed and result in creating a different critical path. Always revisit the project schedule to ensure the schedule has been crashed.

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟