Which of the following lists the inputs and the tools and techniques that the two processes within the Initiating process group share?

A. Project SOW, enterprise environment factors, and organizational process assets

B. Project SOW, enterprise environment factors, organizational process assets, project selection methods, and expert judgment

C. Project SOW, enterprise environment factors, organizational process assets, project management methodology, PMIS, and expert judgment

D. Enterprise environment factors, organizational process assets, PMIS, and expert judgment

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/09/30
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation:

The Develop Project Charter and Preliminary Scope Statement processes both have the following as inputs: project SOW, enterprise environment factors, and organizational process assets. Both processes share the following tools and techniques: project management methodology, PMIS, and expert judgment.