You are in the process of making project staff assignments. You have several candidates for a position on the project team that requires?

 specific qualifications. All the candidates seem to meet the qualifications. You also consider personal interests, characteristics, and availability of these potential candidates. Which of the following is true?

A. You are considering the roles and responsibilities input of the Acquire Project Team process.

B. You are considering the staffing management plan input of the Develop Project Team process.

C. You are considering the organizational process assets input of the Develop Project Team process.

D. You are considering the enterprise environmental factors input of the Acquire Project Team process.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/10/06
KRND MLRDO
من قبل KRND MLRDO

Tired of struggling with your essays? We feel you, homie. We know how frustrating it can be to spend hours researching, writing and editing, only to get mediocre grades. But don't worry, we're here to take the wheel and help you cruise through your essays. Team of experts from https://educibly.com/ knows the ins and outs of essay writing and can help you craft a winning essay that will impress your professor. With our help, you can finally say goodbye to the struggle and hello to good grades. So, let's team up and make your essay journey smooth like butter.

naveed noor
من قبل naveed noor , cargo agent , Etihad Airways

the present project and render him assistance if necessary.

Mutale Mutale
من قبل Mutale Mutale , General Foreman , MOPANI COPPER MINES

You are considering the organizational process assets input of the Develop Project Team process.

Mohamed Faisal
من قبل Mohamed Faisal , senior designer , mcdermott

support and achieving a common goal ‎

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: D

Explanation: The enterprise environmental factors input of the Acquire Project Team process considers elements such as personal interests, characteristics, and availability of potential team members.