Your company provides answering services for several major catalog retailers. The number of calls coming into the service center per month has?

 continued to increase over the past months. The phone system is approaching the maximum load limits and needs to be upgraded. You've been assigned to head up the upgrade project. Based on the company's experience with the vendor who worked on the last phone upgrade project, you're confident they'll be able to assist you with this project as well. Which of the following is true?

A. Vendor availability and expertise are constraints. The project came about because of a business need.

B. You've made an assumption about vendor availability and expertise. The project came about because of a market demand.

C. You've made an assumption about vendor availability and expertise. The project came about because of a business need.

D. Vendor availability and expertise are constraints. The project came about because of a market demand.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/08/11
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation: The project came about because of a business need. The phones have to be answered because that's the core business. Upgrading the system to handle more volume is a business need. An assumption has been made regarding vendor availability. Always validate your assumptions.